Marine operations and logistics: installing and maintaining at sea

Vessels, ports, weather windows and slack water: why getting machines into the sea and keeping them running is one of the biggest costs in wave and tidal energy, and how planners model it.

On this page
  1. The weather window
  2. Vessels and ports
  3. Strategies for maintenance
  4. Modelling it

Every phase of an ocean-energy project involves boats: surveying the site, laying cables, placing foundations and anchors, towing out and connecting devices, inspecting and repairing them for twenty years, and finally removing them. The cost and risk of these marine operations can rival the cost of the machines themselves.

The weather window

Each operation has limits: a maximum wave height, wind speed or current speed above which it cannot be done safely, and a minimum duration. A "weather window" is a period during which conditions stay within those limits long enough to finish the job, including transit to and from port. Wave sites are chosen because they are energetic, which means windows are scarce, especially in winter. Tidal sites add a second clock: heavy work in the flow is often only possible around slack water, which may last well under an hour, twice a day.

Planners use long time series of metocean data to estimate how often windows occur in each month and how long a given operation is likely to wait. These statistics drive everything from installation schedules to the size of the maintenance budget.

Vessels and ports

Operations need vessels matched to the job: multicat workboats for moorings and small lifts, anchor handlers, cable-laying vessels, jack-up barges and, for big tidal foundations, dynamic positioning vessels able to hold station in strong currents. Large vessels are expensive and in demand from offshore wind and oil and gas, so their day rates and availability can shape a project. A nearby port with deep water, quayside space and cranes is just as important; a long transit eats into every weather window.

Strategies for maintenance

  • Corrective maintenance waits for something to break. It is cheap to plan and costly when it happens.
  • Preventive maintenance replaces parts on a schedule, ideally in summer when access is easier.
  • Condition-based maintenance uses sensors to predict failures and intervene before they cause downtime.
  • Retrieval to port designs devices to be disconnected and towed to shore for any significant work, turning offshore repairs into easier quayside ones.

Modelling it

Logistics models combine the work plan, vessel options, port locations, weather statistics and failure rates from reliability analysis to estimate both cost and downtime. The output feeds directly into availability, annual energy and the levelised cost of energy. Many early projects underestimated these costs badly, which is one reason design tools now treat logistics as a core module rather than an afterthought.